I’m doing a bathroom renovation. The tub is a soaker jacuzzi tub. So there’s wiring and plumbing that need to be done. But the way the tub sits it will be surrounded by tile. Similar to what you see in this photo: http://www.admiralvillage.com/images/web%20res/16%20Main-Soaker-Tub-2.jpg So my question is do I do the tile work first? Or do I install the tub first? See the soaker tub has a certain edge to it that would seem to make sense that it should sit on top of the tile. But if I do the tiling first then how does one complete the hookups and electrical? Maybe as I think about it it should be done in stages like Take the deck, the install tub, the after it’s hooked up and tested, then tile in the rest? Am I on the right track here. Again look at the photo. Mine is going to be almost identical to that. Thanks.
Do I put the tub in first or do I do the tile first?